Project Highlights – September 2021

Beck & Bellucci (B&B) is looking to complete the installation of the King Pile retaining wall along US Route 202.B&B subcontractor, Weaver Bros, is going to continue removal of the temporary access road and install large rocks along the face of the King Pile Wall to prevent scouring by the river.B&B is constructing sidewalks on … Continue reading Project Highlights – September 2021

Project Highlights – October 2021

A current list of work items that Beck & Bellucci (B&B) and their subcontractor will be constructing over the next 2 weeks. Construction will continue at the transcript damJCB Colby will continue placing stone on the bridgeB&B will continue working on the rail support slab on US 202HUB Foundation will continue installing micropiles along the … Continue reading Project Highlights – October 2021

Flooding at Construction Site

As in many areas throughout New England, heavy rain began in Peterborough on the evening of December 24th, and continued into the morning of December 25th. The project contractor for the Main Street Bridge Project had prepared for this storm based on the anticipated rainfall. As a result of this storm, the construction site received approximately 2 inches … Continue reading Flooding at Construction Site

Main Street Bridge Officially Closed to Motorists

The Bridge is officially closed to all vehicle traffic as of Monday, April 27th. The south sidewalk will remain open until the temporary pedestrian bridge is installed. Weather and circumstances permitting, work through Friday, May 15th will include: Striping/painting Main St. and adjacent parking spacesInstallation of barrier for staging area in front of Bar Harbor … Continue reading Main Street Bridge Officially Closed to Motorists

Main St. Bridge Full Closure Scheduled for April 13th

The full closure of the Main St. Bridge is scheduled to begin on Monday, April 13th, 2020 at 7:00 AM. The bridge will not reopen again until the project is complete. The Main St. Bridge and Route 202 reconstruction work is expected to be a two-year project.A comprehensive sign package will be installed prior to … Continue reading Main St. Bridge Full Closure Scheduled for April 13th